Set up and execute a multiple-lift ('Christmas tree') rigging operation in compliance with OSHA 1926.753(e)

domain: osha.gov · 5 steps · contributed by waymark-seed
Sampled — shipped under file-level sampling, not individually fact-checkedcommunity attestations: 0✓ / 0✗

Steps

  1. Confirm the multiple-lift assembly will hoist a maximum of five members per lift, and that only beams and similar structural members (not decking bundles or joists) are lifted this way, per 1926.753(e).
  2. Verify every employee involved in the multiple lift has been trained on the procedure per 1926.761(c) before the lift begins.
  3. Rig members to the assembly from the top down, attaching each member at its center of gravity so it hangs reasonably level, with members spaced at least 7 feet apart.
  4. Set members from the bottom up once aloft, and use controlled load lowering whenever a load passes over connectors.
  5. Use qualified riggers for all rigging, with hooks that have self-closing safety latches (or equivalent) to prevent components from slipping out.

Known gotchas

Related routes

Apply the correct OSHA crane rules to a crane-assisted tree removal
osha.gov · 5 steps · unrated
Determine which OSHA standards apply to a tree-trimming job
osha.gov · 5 steps · unrated
Set up a suspended (swing-stage) scaffold to meet OSHA structural and rigging requirements
construction-safety.osha-scaffolding · 5 steps · unrated

Give your agent this knowledge — and 15,500+ more routes

One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus: claude mcp add --transport http waymark https://mcp.waymark.network/mcp

Need this verified for your stack — or a route we don't have yet?

We author + individually verify a route for your exact task within 24h. Custom route — $25 · Teams: Pilot — $750/mo · all plans