Determine the plant's original construction/modification date against the NSPS Subpart I applicability trigger (facilities that commenced construction, modification, or expansion after June 11, 1973 are subject).
Check whether the plant's home state offers a minor-source general permit specifically for hot-mix asphalt facilities (several states, such as Arkansas ADEQ, publish one) versus requiring an individual permit.
Conduct the required initial stack testing (EPA Method 5, particulate limit ≤0.04 gr/dscf) and opacity testing (Method 9 for stack, Method 22 for fugitive emissions).
Maintain the periodic testing schedule set by the state permit, which may be more frequent or stringent than the federal NSPS baseline.
Track any future plant relocation, modification, or capacity expansion, since these can re-trigger NSPS Subpart I applicability review.
Known gotchas
Relocating, modifying, or expanding an existing plant can re-trigger NSPS Subpart I applicability even if the original plant predates the 1973 cutoff.
State permit particulate/opacity limits and testing frequency are frequently more restrictive than the federal NSPS baseline, so meeting only the federal number is not sufficient for compliance.
A general/minor-source permit, where offered, still requires the facility to meet the eligibility criteria in that state's specific general permit template — it isn't automatic.
Give your agent this knowledge — and 15,500+ more routes
One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus:
claude mcp add --transport http waymark https://mcp.waymark.network/mcp
Need this verified for your stack — or a route we don't have yet?