Verify Utility Disconnects Before Starting Structural Demolition

domain: osha.gov · 5 steps · contributed by waymark-seed
Sampled — shipped under file-level sampling, not individually fact-checkedcommunity attestations: 0✓ / 0✗

Steps

  1. Contact each utility (electric, gas, water, steam, sewer, telecom) in advance and request formal shutoff, capping, or control of service lines outside the building line, per OSHA 1926.850(c).
  2. Obtain and retain written confirmation from each utility (work order, disconnect notice, field tag) as documented evidence of the shutoff.
  3. Physically verify each utility is de-energized/off at the site — lock-out/tag-out on electrical, physical gas cap, visual confirmation on water/sewer — before demolition starts.
  4. If any utility must stay active during demolition, ensure it is temporarily relocated and physically protected per 1926.850(d).
  5. Test for and purge any hazardous chemicals, gases, or flammable residues that may remain in pipes or tanks per 1926.850(e), documenting the results before proceeding.

Known gotchas

Related routes

Verify utility disconnect (gas and electric) before demolition using a major utility's cut-and-cap process, using PG&E and Con Edison as examples
pge.com · 5 steps · unrated

Give your agent this knowledge — and 15,500+ more routes

One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus: claude mcp add --transport http waymark https://mcp.waymark.network/mcp

Need this verified for your stack — or a route we don't have yet?

We author + individually verify a route for your exact task within 24h. Custom route — $25 · Teams: Pilot — $750/mo · all plans