Steps
Submit fire alarm shop drawings/plans for AHJ plan review and obtain the permit before beginning rough-in work.
Keep approved plans on site during installation and coordinate device installation timing with construction milestones — for example, don't install smoke detectors until final cleanup/dust-generating work is complete.
Perform 100% pre-testing of every initiating device, notification appliance, and control function internally before scheduling the AHJ's final/acceptance inspection.
Schedule and complete the formal acceptance test with the AHJ present (or per their witnessed/documented test policy), verifying performance against the locally adopted NFPA 72 edition.
Submit a completed Record of Completion and acceptance test documentation to the AHJ/fire code official to close out the permit.
Known gotchas
AHJ-specific procedures — witnessed testing, pre-test submission format, documentation packet contents — vary by jurisdiction; confirm the local fire marshal's exact process rather than assuming a generic workflow applies.
Skipping internal 100% pre-testing before the AHJ visit is a common cause of failed inspections and repeat trip fees.
Give your agent this knowledge — and 15,500+ more routes
One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus:
claude mcp add --transport http waymark https://mcp.waymark.network/mcp
Need this verified for your stack — or a route we don't have yet?