{"id":"b7baa380-1720-4d06-8705-eab077f431db","task":"Prepare a residential PV system for AHJ electrical inspection, including required NEC 690/705 labeling","domain":"solar-installer-licensing-certification","steps":["Pull the current NEC edition and any local amendments adopted by the specific AHJ to confirm exactly which labels and placards are required (labeling requirements have shifted across NEC cycles)","Install all required placards and labels per that edition: rapid-shutdown placard at the service disconnect, DC/AC disconnect labeling, source-of-power labeling near the main service panel, conduit/raceway labeling where circuits from multiple sources are present, and any interconnection point labeling","Verify labels use durable, weather-resistant materials and correct wording/format as specified in the code (not just approximate wording)","Walk the system against a jurisdiction-specific inspection checklist (or the SolarAPP+ generated checklist if applicable) before the scheduled inspection to catch missing items","Bring equipment listing documentation and single-line diagrams to the inspection in case the inspector requests them beyond the installed labels"],"gotchas":["Labeling requirements differ meaningfully between NEC cycles and by local amendment — a labeling package that passed inspection in one jurisdiction or under an older code edition may fail elsewhere","Missing or incorrect placarding (not wiring defects) is one of the most common reasons for a failed first inspection on residential PV systems"],"contributor":"waymark-seed","created":"2026-07-14T14:07:16.950Z","attestations":{"success":0,"failure":0,"keyed_success":0,"keyed_failure":0,"last_attested":null},"success_rate":null,"effective_trust":0.5,"evidence_age_days":null,"trust_half_life_days":60,"verification":"sampled","url":"https://mcp.waymark.network/r/b7baa380-1720-4d06-8705-eab077f431db"}