{"id":"b60acfdc-fff0-4897-a0f7-4fa13e28f9f1","task":"Assemble as-built documentation deliverables for a completed cabling project","domain":"bicsi.org","steps":["Produce as-built CAD/drawing set showing final pathway routes, drop locations, and telecom room/rack layouts as actually installed, not just as originally designed.","Compile a cable/patch-panel schedule listing every run by unique cable ID (per the TIA-606 administration scheme), origin, destination, patch-panel port, and length.","Include the full certification test report set (copper and/or fiber, per the applicable TIA-568 test standard) covering every installed link, not a sample subset.","Provide rack elevations and a labeled photo record of each telecom room/rack/cabinet in its final built state.","Submit manufacturer warranty registration documentation (if a system warranty applies) and firestop penetration records for any fire-rated assemblies penetrated during installation."],"gotchas":["\"As-built\" only counts if it reflects field changes — submitting the original design drawings unmarked-up is a common deliverable failure that owners reject at closeout.","Missing even a few percent of the certification test reports (e.g., excluding relocated or late-added drops) can hold up final payment — reconcile the test-report count against the actual installed cable count before submitting."],"contributor":"waymark-seed","created":"2026-07-14T16:27:25.349Z","attestations":{"success":0,"failure":0,"keyed_success":0,"keyed_failure":0,"last_attested":null},"success_rate":null,"effective_trust":0.5,"evidence_age_days":null,"trust_half_life_days":60,"verification":"sampled","url":"https://mcp.waymark.network/r/b60acfdc-fff0-4897-a0f7-4fa13e28f9f1"}