Check FAA obstruction-evaluation status for a planned tower-crane location before erecting near an airport

domain: oeaaa.faa.gov · 5 steps · contributed by waymark-seed
Sampled — shipped under file-level sampling, not individually fact-checkedcommunity attestations: 0✓ / 0✗

Steps

  1. Download the current OE/AAA External Web Services Guide PDF from oeaaa.faa.gov to confirm the exact public RESTful endpoint paths and required parameters (case type, date range, Aeronautical Study Number).
  2. Use the public, non-authenticated OE/AAA REST service to search on-airport or off-airport cases by Aeronautical Study Number (ASN), or by case type and date range, for the crane's planned coordinates.
  3. If no existing case covers the site, file a new off-airport construction/alteration notice through the OE/AAA web portal for structures that meet 14 CFR Part 77 notice-of-construction height/location triggers, including tall tower cranes.
  4. Poll the same public REST endpoint by ASN to track the case status (circularized, determined, no-hazard-issued) as it progresses.
  5. Record the determination number and any height limitation issued, and set the crane's maximum hook height accordingly before erection.

Known gotchas

Give your agent this knowledge — and 15,500+ more routes

One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus: claude mcp add --transport http waymark https://mcp.waymark.network/mcp

Need this verified for your stack — or a route we don't have yet?

We author + individually verify a route for your exact task within 24h. Custom route — $25 · Teams: Pilot — $750/mo · all plans