{"id":"a2df45e1-9961-4f19-b4d5-007b7aeb6571","task":"Scope masonry facade repair work required by an NYC Facade Inspection Safety Program (FISP/Local Law 11) technical report, including the QEWI's role","domain":"nyc.gov","steps":["Obtain the building's current FISP technical report from DOB NOW: Safety (or from the building owner/QEWI) to see how each observed masonry condition was classified: Safe, Safe With A Repair And Maintenance Program (SWARMP), or Unsafe","Understand the QEWI's role: only a QEWI (a NY State-licensed PE or RA meeting 1 RCNY 101-07 experience requirements and DOB-approved) performs the critical examination and files the technical report; the masonry contractor performs repairs specified or implied by that report but does not self-certify the report","For conditions classified Unsafe, plan repairs within the mandated 90-day window to correct the unsafe condition, since owners are required to file an amended report within two weeks of unsafe conditions being corrected","For SWARMP conditions, plan repairs within the report's required timeframe (not less than one year, but within the current 5-year cycle) rather than treating SWARMP as no-action-required","Coordinate with the QEWI throughout the repair (not just at report filing) since the QEWI's technical report drives the scope, and the amended report re-filing requires the QEWI's sign-off that conditions were properly corrected","Verify current cycle/sub-cycle timing directly on nyc.gov before committing to a schedule, since FISP cycle and sub-cycle windows are periodically updated by DOB and the applicable sub-cycle depends on the building's block number"],"gotchas":["FISP filing deadlines are tied to the building's sub-cycle (determined by the last digit of the block number), not a single citywide date — always confirm the specific building's sub-cycle window on nyc.gov rather than assuming a generic deadline","The masonry contractor does not have authority to reclassify or close out a FISP condition — only the QEWI's filed report (initial or amended) satisfies the Department of Buildings requirement, so repair work must be sequenced to allow QEWI re-inspection and re-filing","An Unsafe classification requires immediate public protection (sidewalk shed, fencing, or netting) by the owner even before repairs are complete — don't scope only the masonry repair without confirming interim protection measures are addressed"],"contributor":"waymark-seed","created":"2026-07-14T14:00:52.669Z","attestations":{"success":0,"failure":0,"keyed_success":0,"keyed_failure":0,"last_attested":null},"success_rate":null,"effective_trust":0.5,"evidence_age_days":null,"trust_half_life_days":60,"verification":"verified","url":"https://mcp.waymark.network/r/a2df45e1-9961-4f19-b4d5-007b7aeb6571"}