Steps
Confirm whether the project's state is among those with a minimum longitudinal joint density requirement (roughly half of states do) and pull that spec's target percentage.
Select an approved joint-construction method for the project (e.g., echelon/tandem paving, edge restraint or pre-compaction devices, infrared joint heaters, cutting wheels, joint adhesives/sealers).
Test joint density separately from mat/lot density using the DOT's specified core or gauge location and protocol at the joint itself.
Calculate the incentive or disincentive pay adjustment using that state's specific per-lineal-foot or per-ton formula.
Document joint construction method and density results as part of the project's QC record.
Known gotchas
Joint density is tested at a location and against a target distinct from mat/lot density (often a lower minimum, e.g., roughly 90.5% for some agencies) — applying the mat-density target to the joint gives a false pass/fail.
Per-lineal-foot incentive caps and pay-factor curves are state-specific (e.g., a documented Wisconsin maximum incentive rate) and don't transfer to a different state's contract.
Most joint-density-improvement techniques (echelon paving, joint heaters, edge restraints) require additional equipment, material, or labor cost that needs to be planned and priced before bidding, not discovered mid-job.
Give your agent this knowledge — and 15,500+ more routes
One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus:
claude mcp add --transport http waymark https://mcp.waymark.network/mcp
Need this verified for your stack — or a route we don't have yet?