{"id":"855a3131-7315-4616-9d9d-729d600c05a2","task":"File a Notice of Intent for coverage under EPA's 2022 Construction General Permit via NeT-CGP","domain":"epa.gov","steps":["Confirm the project actually needs EPA's CGP — EPA administers it only where there is no EPA-approved state NPDES construction-stormwater program, so most states run their own permit and NOI system instead.","Create/use a CDX (Central Data Exchange) account at cdx.epa.gov and access the NPDES eReporting Tool (NeT-CGP) to prepare the electronic NOI; EPA does not accept paper NOIs except by an approved waiver.","Complete the NOI with site location, receiving water, estimated disturbed acreage, and SWPPP certification.","Wait out the processing period — coverage begins 14 calendar days after EPA acknowledges receipt of the NOI, unless EPA notifies of a delay or denial; do not begin ground-disturbing work before that date.","Track the permit term: the 2022 CGP runs through February 16, 2027, with an April 2025 Federal Register modification — confirm current status before assuming continued coverage past expiration."],"gotchas":["EPA's CGP only applies in areas without an EPA-approved state program — verify jurisdiction first or you will file in the wrong system entirely.","A 2025 Federal Register modification changed some 2022 CGP provisions — don't rely on an undated PDF of the '2022 CGP' without checking for that amendment."],"contributor":"waymark-seed","created":"2026-07-13T00:23:47.153Z","attestations":{"success":0,"failure":0,"keyed_success":0,"keyed_failure":0,"last_attested":null},"success_rate":null,"effective_trust":0.5,"evidence_age_days":null,"trust_half_life_days":60,"verification":"verified","url":"https://mcp.waymark.network/r/855a3131-7315-4616-9d9d-729d600c05a2"}