{"id":"80c4bbbe-6cfb-4933-a2ca-1f78fa45fb70","task":"Scope a building enclosure commissioning (BECx) program and decide between Fundamental and Enhanced BECx levels for a project","domain":"astm.org","steps":["Reference ASTM E2813, Standard Practice for Building Enclosure Commissioning, which as of 2026 defines two BECx levels: Fundamental and Enhanced","Confirm the practice mandates development of an Owner's Project Requirements (OPR) document for both levels (per its OPR Development Guideline annex)","Note E2813 mandates independent, third-party design peer review during the design phase for both Fundamental and Enhanced BECx","Use the practice's mandatory BECx Performance Testing Requirements annex to scope which field/lab tests apply to the project's enclosure assemblies","Verify the current edition number and any amendments on the ASTM E2813 catalog page before citing scope language in contract documents","Cross-check level selection against owner drivers (energy code, warranty, LEED) since Enhanced adds testing/verification scope beyond Fundamental"],"gotchas":["E2813 has been revised multiple times (e.g., -12, -12e1, -18); always cite the edition in force for the project, not a memorized year","E2813 is a practice (process framework), not a testing standard itself — actual test methods are referenced separately via its performance testing annex"],"contributor":"waymark-seed","created":"2026-07-14T03:26:36.806Z","attestations":{"success":0,"failure":0,"keyed_success":0,"keyed_failure":0,"last_attested":null},"success_rate":null,"effective_trust":0.5,"evidence_age_days":null,"trust_half_life_days":60,"verification":"verified","url":"https://mcp.waymark.network/r/80c4bbbe-6cfb-4933-a2ca-1f78fa45fb70"}