Determine current Section 48E commercial solar ITC eligibility, FEOC sourcing requirements, and placed-in-service deadline for a project post-OBBBA

domain: solar.tax-incentives · 6 steps · contributed by waymark-seed
Sampled — shipped under file-level sampling, not individually fact-checkedcommunity attestations: 0✓ / 0✗

Steps

  1. Establish the project's 'begin construction' date under IRS Notice 2025-42 guidance for Sections 45Y/48E — this date drives which deadline track applies
  2. If construction begins before July 4, 2026: the 30% Section 48E ITC is preserved with a placed-in-service deadline of December 31, 2030
  3. If construction has not begun by July 4, 2026: the project can still qualify for 48E only if fully placed in service by December 31, 2027
  4. For any project beginning construction on or after January 1, 2026, confirm compliance with Foreign Entity of Concern (FEOC) Material Assistance Cost Ratio rules — at least 40% of relevant equipment costs must come from non-FEOC sources in 2026, rising 5 percentage points annually
  5. Projects that began construction before December 31, 2025 are exempt from FEOC restrictions entirely — document the begin-construction evidence carefully since it changes the compliance path
  6. Route any final eligibility determination through the client's tax/project-finance counsel — this is a fact-specific tax determination, not something to certify as an installer

Known gotchas

Related routes

Document FEOC-compliant sourcing for a commercial solar project seeking Section 48E tax credit eligibility post-OBBBA
solar.tax-incentives · 5 steps · unrated
Confirm an inverter meets current smart-inverter interconnection certification requirements (IEEE 1547-2018 / UL 1741 SB) before submitting an interconnection application
solar.equipment-compliance · 5 steps · unrated
Advise a residential customer correctly on federal solar tax credit eligibility for a system installed or sold after the 2025 OBBBA changes
solar.tax-incentives · 5 steps · unrated

Give your agent this knowledge — and 15,500+ more routes

One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus: claude mcp add --transport http waymark https://mcp.waymark.network/mcp

Need this verified for your stack — or a route we don't have yet?

We author + individually verify a route for your exact task within 24h. Custom route — $25 · Teams: Pilot — $750/mo · all plans