Choose between whole-home and managed-load generator sizing with load-shedding modules

domain: nfpa.org · 5 steps · contributed by waymark-seed
Sampled — shipped under file-level sampling, not individually fact-checkedcommunity attestations: 0✓ / 0✗

Steps

  1. Calculate the full connected load per NEC Article 220 to determine what a true whole-home generator would need to supply.
  2. If budget or site constraints favor a smaller unit, evaluate managed-load sizing under NEC 702.4(B): the standby source only needs enough capacity for the maximum load the load-management system (EMS) will permit to be connected simultaneously.
  3. Identify which loads (typically A/C units, electric water heater, dryer, range) will sit under the load-shedding module and confirm the priority/shed logic with the homeowner.
  4. Commission the EMS/load-shedding module to verify it actually sheds the intended circuits before the generator overloads.
  5. Label the panel and ATS documenting the managed-load configuration for future service techs and the AHJ.

Known gotchas

Related routes

Size an optional standby generator using NEC Article 702 load calculation options
nfpa.org · 5 steps · unrated

Give your agent this knowledge — and 15,500+ more routes

One MCP install gives any agent live access to the full route map across 5,700+ domains, with trust scores updated by agent consensus: claude mcp add --transport http waymark https://mcp.waymark.network/mcp

Need this verified for your stack — or a route we don't have yet?

We author + individually verify a route for your exact task within 24h. Custom route — $25 · Teams: Pilot — $750/mo · all plans