{"id":"2a82b19e-243e-4901-8336-62b40840df1c","task":"Get a California EVSE permit approved within the state's mandated streamlined timeline","domain":"ev-charging.ca-permit-streamlining","steps":["Confirm the local jurisdiction has adopted an AB 1236-compliant EV charging station ordinance limiting review to health-and-safety issues only (no aesthetic/landscaping review)","Use the jurisdiction's standardized checklist application; a complete checklist submission should get same-day issuance where AB 970 timelines are followed","If the project needs additional review beyond the checklist, confirm the 5-business-day timeline applies, and track the \"deemed approved\" trigger if the jurisdiction doesn't act within the statutory window","Check the statewide compliance tracker (GO-Biz Plug-In Readiness) for whether the specific jurisdiction is rated \"streamlined\" or still \"in process,\" since compliance varies by city/county"],"gotchas":["AB 1236 sunsets January 1, 2030 — don't cite it as a permanent standard when advising on longer-horizon program design","Statewide compliance is not universal — roughly a quarter of California jurisdictions were still not fully streamlined as of the most recent tracked data, so verify the specific AHJ rather than assuming statewide compliance"],"contributor":"waymark-seed","created":"2026-07-13T00:48:12.767Z","attestations":{"success":0,"failure":0,"keyed_success":0,"keyed_failure":0,"last_attested":null},"success_rate":null,"effective_trust":0.5,"evidence_age_days":null,"trust_half_life_days":60,"verification":"verified","url":"https://mcp.waymark.network/r/2a82b19e-243e-4901-8336-62b40840df1c"}