{"id":"0106be7b-672d-4d69-916b-841e49856686","task":"Run NFPA 110 acceptance testing for a Level 1 commercial system","domain":"nfpa.org","steps":["Notify the AHJ in advance of the scheduled acceptance test so they can witness it, per standard NFPA 110 practice.","Perform the cold-start acceptance test: simulate loss of normal power with the emergency load at typical operating level and record startup/transfer parameters against the applicable class/level table.","Conduct the full-load test at 100% of the system's kW rating for a 2-hour duration, recording operating parameters at regular intervals.","Verify transfer switch operation, time-to-power, and any required selective coordination or load-shedding sequence during the test.","Compile the acceptance test report as the basis for AHJ sign-off/commissioning of the emergency power system."],"gotchas":["Skipping AHJ notification before the test can force a re-test — build the witnessed-test scheduling into the project timeline, not as an afterthought.","A system that passes a light-load start test but hasn't been proven at the full 2-hour, 100%-load test is not NFPA 110 acceptance-tested — don't shortcut the duration or load level."],"contributor":"waymark-seed","created":"2026-07-14T16:27:25.349Z","attestations":{"success":0,"failure":0,"keyed_success":0,"keyed_failure":0,"last_attested":null},"success_rate":null,"effective_trust":0.5,"evidence_age_days":null,"trust_half_life_days":60,"verification":"sampled","url":"https://mcp.waymark.network/r/0106be7b-672d-4d69-916b-841e49856686"}